Building Work Status
1.
BUILDING CONSTRUCTION STATUS15 July.
BUILDING LIST
08
COUNT
B07 : Railway Station Control Room
B09-1 : Clinic
B10 : Canteen
B11-1 : Fire Station
B11-2: 2 Windows Training Tower
B14 : MCR
B15 : SS-1
B17 : SS-3
B18 : SS-4
B19 : SS-5
B20 : RIB-1
B21 : RIB-2
B22 : RIB-3
B23 : RIB-4
B24 : Fire Pump Building
B25 : Water Treatment Building
B26 : Crystallizer Building
B27 : Effluent Treatment Building
B28 : Deoiling Building
B29 : Sludge Dewatering Building
B30 : LAB & Amenity Building
B31 : Refuel Service Building
B32 : Potable Water Building
B33 : ATM Vent Treatment Building
B34-1: Gas Service Station
B34-2 : Gas Smoke Chamber
B35 : Operator Shelter
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
5
30
NUMBERING LEGEND
00 SHELTER
1
1
1
2
1
1
1
1
1
1
2
1
1
1
2
1
1
1
1
2
2
1
1
1
1
1
1
1
33
07
35-1
01
04
11-1
11-2
23
UNIT 76
09-1
09-2
34-3
29
27
30
14
10
28
34-2
34-1
25
26
35-2
24
UNIT 83
UNIT 50
UNIT 73
21
32
25
19
19
24
15
27
21
26
33
UNIT 77
SHELTER LIST
S01 : Catalyst Shelter
S04 : Chemical Storage Shelter
S07 : Chemical Rail Wagon
S08 : Product Rail Loading
S10 : U20 Compressor Shelter
S11 : U30 Compressor Shelter-1
S12 : U30 Compressor Shelter-2
S15 : U45 Pre-coat Loading shelter
S17 : U50 Compressor Shelter-1
S18 : U50 Compressor Shelter-2
S19 : Steam Turbine Generator
S20 : U74 Chemical Dosing Shelter
S21 : U72 Chemical Dosing Shelter
S22 : U72 Chemical Dosing Shelter
S23 : U20 Chemical Dosing Shelter
S24 : U75 Compressor Shelter
S25 : U77 Chemical Dosing Shelter
S26 : U77 Chemical Dosing Shelter
S27 : U84 Chemical Dosing Shelter
S30 : U20 Chemical Dosing Shelter
S31 : U30 Chemical Dosing Shelter
S33 : Weathering Shelter
S34: U60 Chemical Dosing Shelter-1
S35: U60 Chemical Dosing Shelter-2
S36 : Fresh Catalyst Package Shelter
S37 : Spent Catalyst Shelter
B09-2 : Clinic Car Parking
B34-3 : Training Ground
07
08
UNIT 84
00 BUILDING
UNIT 91
UNIT 71
35-4
17
UNIT 30
UNIT 40
18
UNIT 20
23
23
22
18
22
11
12
UNIT 81
19
35
15
20
UNIT 10
UNIT 35
31
34
35-5
30
30
UNIT 45
UNIT 60
UNIT 78
UNIT 72
36
31
37
UNIT 74
10
17
35-3
20
33
SUMMARY BUILDING WORK
1. Design Status
▪ Building total : 63 EA
- Building 30 EA, Shelter 33 EA
▪ Total Con’c Quantity : 56,078 m3
▪ Issued AFC : 63 EA
ACTIVITY LEGEND / Перечень Работ
2. Construction Status
▪ Con’c Progress 62.6 % (Done 35,407 m3)
▪ Active Building : 56 EA
(Earth 3, FDN: 11, Above: 42 )
Issued AFC DWG
Upper Structure Work
External Finishing Work
Excavation
Masonry & Plastering Work
Interior Finishing Work
Foundation Work
Steel Erection Work