LECTURE 11Cast-in-Place Piles and
Underground Structures
Construction technology, quality control and
safety
Prepared by: S. Niyetbay
2.
OVERVIEWLecture structure
40
Cast-in-place piles
Pile formation inside a drilled or driven cavity
41
Pile caps and
grillages
Preparation and connection of pile heads
42
Quality control
Inspection, tolerances and acceptance records
43
Underground
structures
Open excavation, diaphragm wall and sinking methods
44
Safety
Equipment, exclusion zones and work controls
02
3.
Cast-in-place pile systemsCast-in-place piles form the shaft at its
design position by placing concrete, soil or
sand into a prepared cavity.
Bored
rotary drilling followed by reinforcement
and concreting
Pneumatic
concrete placed under compressed-air
pressure
Vibrocompacted
casing and concrete compacted by
vibration
Frequencycompacted
casing driven and concrete
compacted by repeated impacts
Sand or soilconcrete
weak ground improved with compacted
columns
03
4.
Bored pile construction sequenceTypical sequence
Drill the shaft to the design depth
Stabilize the bore when required
Form an enlarged base if specified
Install the reinforcement cage
Place concrete through a tremie or
vertical pipe
Form and protect the pile head
4–5
cutting and soil-removal cycles may form
an enlarged base about 1.6 m in diameter
04
5.
Bored pile dimensions and bore stability400–1,200 mm
up to 30 m
typical pile diameters listed
for industrial construction
typical maximum length in
the described systems
880–1,200 mm
up to 35 m
large bored-pile diameters
length of large bored piles
Stable soils allow an uncased dry bore.
Unstable or water-bearing soils require clay
slurry or temporary casing.
05
6.
Special cast-in-place pilemethods
Camouflet enlargement
An explosive charge forms a spherical base
cavity that the concrete immediately fills.
1.2–1.5 m
casing end remains
above the bore bottom
before the charge is
fired
Pneumatic placement
0.25–0.30 MPa
constant air pressure
during concrete placement
06
7.
CHAPTER 40Vibro- and frequency-compacted piles
4–6
m
typical depth of vibro-
0.8–1.0
m
initial concrete layer
compacted piles in
dry cohesive soils
placed inside the
casing
4–5
cm
upward casing
2–3
cm
downward movement
movement during
impact compaction
during the next
impact
Repeated movement compacts the
fresh concrete against the bore
wall and densifies the surrounding
soil.
07
8.
CHAPTER 40Sand and soil-concrete piles
Sand piles improve weak soil by replacing and
compacting soil inside a driven casing. Flexible
petals at the casing tip open during withdrawal.
up to 7 m
depth of compacted
sand columns
Soil-concrete piles use a hollow drilling rod with a mixing
bit. The tool blends soil with a cement suspension while
withdrawing, so no soil excavation is required.
08
9.
CHAPTER 41Pile heads and grillage construction
The grillage transfers structural
loads to the pile group.
Construction starts with pilehead preparation.
Remove weak or damaged concrete
Expose and preserve the required
reinforcement
Level the pile heads
Install precast beams or cast the
monolithic cap
Complete concrete infill around the pile
connection
Precast grillage beams may connect to
pile reinforcement through grouted
openings.
09
10.
CHAPTER 42Quality control and tolerances
Pile foundations are hidden works. Inspection
must continue throughout drilling, driving,
reinforcement and concreting.
1
cm / 100 m
maximum deviation of
setting-out axes for a
pile row
0.20D
plan deviation for
a single pile row
±50 mm
±30 mm
pile-head tolerance for
a monolithic grillage
pile-head tolerance for
a precast grillage
0.30D
plan deviation for
two- or three-row
groups
D denotes the pile diameter or the maximum side of a
rectangular pile.
10
11.
CHAPTER 42Acceptance records
Acceptance confirms geometry, pile
installation and pile-cap construction.
01
Pile installation
log
driving or cast-in-place operations for each pile
02
Summary register
installed piles and their final positions
03
Survey record
as-built axes and pile-field geometry
04
Test results
dynamic or static pile tests where required
05
Material records
reinforcement, concrete and precast-element certificates
11
12.
CHAPTER 43Methods for underground structures
The construction method depends on
groundwater conditions, depth and sensitivity
of nearby buildings.
Open
excavation
Excavate a pit with slopes or temporary retaining walls. Practical for
relatively shallow work in dry ground.
Diaphragm wall
Construct perimeter walls in slurry-supported trenches, then excavate
inside.
Sinking method
Build a well or caisson at the surface and lower it by removing soil
from below.
Open excavation commonly applies at depths up to about
15 m.
12
13.
CHAPTER 43Diaphragm wall construction
A bentonite slurry supports the
trench walls during excavation.
Reinforcement cages or precast
panels enter the slurry-filled trench
before concreting.
4–6
m
typical length of an
individual trench
panel
2–5 mm
filter cake formed by
suitable clay slurry
Alternating primary and secondary
panels create a continuous wall that
can also act as the permanent
foundation enclosure.
13
14.
CHAPTER 43Sinking wells and caissons
>20 m
1.5–2.0 m³
large well diameter
where excavators
may work inside
typical bucket
capacity described
for soil removal
10–30 kN/m²
approximate wall
friction used in
preliminary checks
≥25%
weight margin
above side
friction during
sinking
A thixotropic slurry jacket can
reduce labor by almost 35% and
total cost by about 15–20%.
14
15.
CHAPTER 44Safety requirements
Safety controls apply to piling equipment,
excavation work and sinking operations.
2.0 m
maximum stack height for rectangular
reinforced-concrete piles
1.5 m
maximum stack height for tubular piles
boom radius + 5 m minimum restricted zone around a piledriving rig
50% above
working pressure pressure test level for jetting pipes and hoses
18 years
minimum age stated for operators of piledriving equipment
15
16.
SUMMARYKey engineering decisions
01
Ground
conditions
Select bore support, casing and concreting method from soil and
groundwater data.
02
Pile integrity
Control bore geometry, reinforcement placement and concrete continuity.
03
Load transfer
Prepare pile heads and detail the grillage connection correctly.
04
Underground
works
Match open, diaphragm-wall or sinking construction to depth and nearby
structures.
05
Safety
Define equipment controls, exclusion zones and emergency procedures
before work starts.